Defects period tracking after practical or substantial completion

The defects period is where an Irish project’s loose ends are either closed out or quietly forgotten. Whether your contract speaks of a Defects Period ending in a Defects Certificate, as the public works contracts do, or of a defects liability period, as many private contracts do, the dates all run from the day the works were taken over. Fidrel counts them from that day, files them in the facilities register beside your other warranties and service contracts, and reminds whoever added them, and the project’s administrators, inside Fidrel before each one falls due.

30 days free · No minimum term.

Facilities management in Fidrel on a laptop, tablet and phone, with the asset register, warranty dates and open fault reports

Why the end of the defects period catches people out

Two contract vocabularies

A public works job talks about the Defects Period and the Defects Certificate, while many private jobs talk about the defects liability period instead. Teams moving between the two carry the wrong words, and sometimes the wrong length of period, from one job to the next.

Month eleven arrives after the team has left

By then the site manager, the design team and often the client’s project manager are busy on other jobs. If the inspection date only lived in one person’s diary, it is arranged in a rush or missed entirely, and the period can close before anyone has walked the building.

Snags left open at handover drift

Items accepted as outstanding on the snag list at completion should be put right during the period, together with whatever the occupants report later. Without one place for both, nobody can say at the final inspection what has actually been fixed.

Three dates on the Irish template

An Irish project starts from three entries. The end-of-defects inspection at 11 months is marked Common practice; the end of the defects liability period at 12 months and the final list of defects at 13 are both marked Under the contract. A short note under the list reminds you to check them against your contract. The length of the period and what closes it come from the contract you signed, so read it before adding anything. The periods are starting values to check against your own contract; Fidrel gives no legal advice on them.

Operations
Warranties & contracts in Fidrel in order of end date, with reminders, notice periods and the Dates after handover button

Public works wording: Defects Period and Defects Certificate

The template’s entries speak of the defects liability period and a final list of defects. On a public works project you can keep the contract’s own terms instead: edit an entry’s title, for instance to Defects Period ends, and add a Warranty entry named Defects Certificate with the date you expect it. If the period is extended under the contract, move the entry’s end date; its reminder is then worked out again from the new date. An entry can also record the contractor as its counterparty, hold the contract reference and link the signed completion certificate from the project’s documents.

Open fault reports in Fidrel with priority, location, the person assigned and the status of each

Dating the defects period in Fidrel

  1. Step 1

    Enter the completion date

    Dates after handover sits on the Warranties & contracts tab of Facilities management. Its date field reads Practical completion on every Irish project; on a public works contract, the substantial completion date goes in that field.

  2. Step 2

    Check the three proposed dates

    Three lines appear, each with a month figure and the date it produces: 11 for the end-of-defects inspection, 12 for the end of the defects liability period and 13 for the final list of defects. Overwrite a figure with anything from 1 to 240, or untick a line your contract has no use for.

  3. Step 3

    Add them and tune the reminders

    Add the dates turns each ticked line into a warranty entry that runs from completion to its end date. At the proposed figures the first two come with a 30-day reminder and the final list with a 90-day one; open an entry to pick any reminder between 0 and 730 days.

Reminders inside Fidrel

Early each morning Fidrel looks through the register for entries that have reached their reminder day. Whoever created the entry, along with the project’s administrators, then receives the notification Agreement nearing its end date, as long as the entry is visible to them, and the entry is marked Ending soon on the list. The facilities overview counts the entries in their notice period. Every reminder stays inside Fidrel as a notification; nothing goes out by email or text message.

Snags and defects reported during the period

The snag list agreed at handover has a line on the Irish checklist and its own folder under 10 Warranties and defects, beside folders for the defects liability period, warranties and guarantees, and latent defects insurance. Anything the occupants report afterwards can be logged as a fault report with a description, its location in the building, a priority and as many as twelve photos; assign it to someone in the project, name the firm doing the repair and set the date it should be fixed by. Before the end-of-defects inspection, the open fault reports and the snag list folder show what is still to be put right.

Manufacturers’ warranties run separately

Boilers, lifts and other plant often carry a manufacturer’s warranty with its own end date, unrelated to the defects period. Each asset in the register has a Warranty until field, and the overview lists the assets whose warranty ends within 90 days. An asset’s Warranty until date triggers no reminder of its own. For any you need to be warned about, add a Warranty entry under Warranties & contracts and link it to the asset.

What Fidrel leaves to the contract and to you

Fidrel issues no Defects Certificate, schedule of defects or final certificate; it only holds the dates you give it. Fidrel drafts no notice or letter to the contractor and leaves the end-of-defects inspection for you to organise. Fault reports are logged through Fidrel in a web browser, on a computer or phone; there is no separate app and nothing is pinned to a drawing.

One project. One subscription. The entire platform included.

Your trial applies to your first own project and starts when that project is created. No card required. Afterwards, choose card or invoice to continue.

  • 30 days free
  • Unlimited participants
  • No minimum term

Defects period

Frequently asked questions

Anything else on your mind? We are happy to help.

Talk to us

That depends on the contract. Fidrel proposes 12 months for the end of the defects liability period as a starting value, but the period your contract states is the one that counts, so change the figure before you add the dates.