Why an older school lands mostly in year one
Fidrel places each replacement in the year its lifespan runs out, counted from the year the school was built, and anything already past that point lands in the programme’s first year. Take a primary school built in 1998 and a ten-year programme starting in 2027. The boilers, lighting, fire alarm system, floor coverings, toilets and washrooms, play equipment, footpaths, external and internal redecoration and the sports hall floor all fall in 2027, because their typical lifespans have already run out. Rainwater goods, entrance doors and fire doors follow in 2028, while windows and roof coverings fall beyond the ten years. No board can do all of that in one summer, so the first real task is to move each first year to when the work is likely to be needed, ideally after someone has looked at the building. Repeating work then comes round on its own interval: external redecoration done in 2027 returns in 2034.