Baseline schedule in construction: the plan you measure against

A baseline schedule is the plan as it stood when it was approved, frozen so that later changes can be measured against it. The current schedule moves every week; the baseline does not. In Fidrel you save a baseline from the schedule, pick it in the View menu, and each activity that has moved shows a thin baseline line beneath its bar, while the end date shows how many days the project has moved.

30 days free · No long-term contract.

The Fidrel schedule with its Gantt chart on a laptop, tablet and phone, bars linked by dependencies and a red line for today

Why teams lose the baseline

The approved plan is overwritten

The schedule is updated every week and nobody saved the version that was approved. When the owner asks how far the finish has slipped, there is nothing to compare with.

Progress mistaken for variance

An activity can be 40 percent complete and still be on its baseline dates, or 80 percent complete and a month late. Percent complete says how much is done, and the baseline says whether the work is happening when it was planned.

A re-baselined plan that hides the slip

When the baseline is reset to match the current plan, the variance returns to zero. Without a record of what was saved and when, a reset is easy to make and hard to notice.

Baseline, current plan, forecast and actual

The baseline is the approved plan frozen. The current plan is the live schedule that the team updates. A forecast is where the current plan says the work will finish, and the actuals are what has really happened: the actual start and finish of an activity and its progress. Variance is the gap between the forecast and the baseline. In Fidrel the current plan and the forecast are the same bars, the baseline is a saved copy, and the progress line shows whether work is ahead of plan, on track or behind plan.

Scheduling
The Gantt chart with a legend that lists planned activity, actual progress, baseline, critical path, milestone and dependencies, and a View menu next to Filter

Baseline variance and planned progress are different checks

Planned progress assumes even progress across the working days of the working calendar, and the actual progress is what the team enters. That compares the work done with the work that should be done by today. The baseline compares dates, not progress: it tells you whether the finish has moved. A schedule can be on track by progress today and still have a positive variance on the end date, because an earlier delay was absorbed and the finish moved.

The key figures of the Fidrel schedule, with the start, end, days remaining and progress of the project

Saving and reading a baseline in Fidrel

  1. Step 1

    Save the baseline once the plan is approved

    Open the More menu in the Schedule and choose Save baseline. The name starts as Baseline with today’s date and can be changed, and Fidrel stores every activity as it stands at that moment.

  2. Step 2

    Choose which baseline to compare with

    Open the View menu and select a baseline under Baseline. Each activity that has moved since then shows a thin gray line under its bar, with the part it now finishes later in orange, and hovering over the line shows the baseline start and finish. Choose the dash to show none.

  3. Step 3

    Read the variance at the end date

    The end date of the schedule shows a Variance in days against the latest end date in the chosen baseline, with a plus sign when the project finishes later and a minus sign when it finishes earlier. The tile Baseline comparison reminds you to select or save a baseline if none is chosen.

  4. Step 4

    Save another when the plan is formally changed

    When an approved change moves the plan, save a new baseline with a name that says so. The earlier baselines stay in the list, so you can compare the current plan with either, and the schedule history records each save.

Who saves a baseline, and what it keeps

Only the people who can edit the schedule, the project’s administrators, save a baseline; everyone who can open the schedule can pick one to compare. A baseline stores each activity that is not archived, together with the working calendar at that moment. Baseline bars also appear under every activity in the PNG, SVG and print views of the schedule when a baseline is selected.

What the baseline in Fidrel does not do

Fidrel shows the variance in days for the schedule’s end date, not as a number on every activity; for an activity that has moved, the baseline line under its bar shows where it was planned. A duplicated schedule does not copy the baselines, so save a baseline again in the copy. A saved baseline is not a contractual or forensic baseline; your contract decides which plan counts. A baseline holds the activities of the schedule, not costs or resources.

One project. One subscription. The entire platform included.

Your trial applies to your first own project and starts when that project is created. No card required. Afterwards, choose card or invoice to continue.

  • 30 days free
  • Unlimited participants
  • No minimum term

Terms

Frequently asked questions

Anything else on your mind? We are happy to help.

Talk to us

The approved schedule saved as a fixed reference. Later updates to the schedule are compared with it, so you can see how far the dates have moved from what was approved.