Guide for owners

How owners set, approve and compare construction cost estimates by design phase

An owner sees several construction cost estimates before a project is built: one at concept or schematic design, an update at design development and another at construction documents, before bids come in. Each is a better picture of the same project, and the owner has to decide which one becomes the budget and see why the number moved between them. This guide walks through that sequence, and shows how Fidrel keeps every estimate, approves one as the baseline and compares the others with it.

30 days free · No long-term contract.

Estimating in Fidrel on a laptop, tablet and phone

Why the budget drifts between design phases

A new total at every milestone

Each design milestone brings an updated estimate from the cost consultant or the design team. The owner sees a new total, but not which line items moved, which scope was added or which allowances were used up.

Several versions, one name

The cost consultant’s estimate, the design team’s update and the owner’s own spreadsheet all call themselves the budget. Nobody can say which one the board approved.

The estimate never becomes the budget

Once approved, the estimate is copied into a separate cost report by hand, and the link between what was estimated and what is now being tracked is lost.

What changes from one design phase to the next

Early in design, an estimate rests on floor areas, building systems and allowances, because much of the building is not drawn yet. As design development and construction documents fill in the details, allowances turn into measured quantities and priced line items, and the contingency held for undefined design scope can come down. The total moves at every step, so the owner needs each estimate beside the one approved before it, not only its bottom line.

Cost estimation
An approved baseline estimate in Fidrel, locked and used as the original budget

Deciding which estimate is the budget

Only one estimate should carry the name budget. In Fidrel each estimate is marked as a baseline, alternate, working or forecast estimate, and approving one as the baseline requires budget and approval rights, which the database checks. The approved estimate is locked and becomes the original budget for cost tracking; from then on changes go through change orders, budget changes or a revision.

Importing an estimate from a CSV or Excel file in Fidrel, with the columns mapped before the rows are imported

Estimates through the design phases, step by step

  1. Step 1

    Set the first budget estimate

    At concept or schematic design, build the owner’s estimate in groups and line items with code, description, quantity, unit and unit price, or import the cost consultant’s CSV or XLSX file.

  2. Step 2

    Approve one estimate as the budget

    When the owner commits to the project, someone with budget and approval rights approves the estimate as the baseline. It is locked and becomes the original budget for cost tracking.

  3. Step 3

    Compare each later estimate with it

    Add the design development and construction documents estimates as numbered revisions and compare each one with the baseline. A revision the owner approves can replace the baseline, keeping approved changes on top or folding them in.

Comparing estimates line by line

Revisions are numbered and the history is kept. Any two estimates can be compared: the comparison shows the line items found in only one of them and the difference on each line, and can be narrowed to the differences only. Markups and deductions such as general conditions, overhead, contingency and profit are added as a percentage or an amount, and a line’s quantity can come from a takeoff on a drawing or a model, flagged when that source changes.

Bringing in the cost consultant’s estimate

Owners often receive their estimates from a cost consultant or the design team. You can paste rows from a spreadsheet or import a CSV or XLSX file, with groups built from levels or codes; an estimate holds up to 5,000 rows. A line’s unit price can be built up from labor, material, equipment, subcontract and other resources, or taken from a vendor quote attached to the line. Every estimate exports to XLSX, CSV or PDF.

What estimating in Fidrel does not do

There is no unit cost library, cost database, assembly library or labor-rate table in Fidrel. Cost codes are free text, with no bundled MasterFormat or Uniformat list. Approval has no e-signature, and Fidrel does not turn an estimate into a client proposal.

One project. One subscription. The entire platform included.

Your trial applies to your first own project and starts when that project is created. No card required. Afterwards, choose card or invoice to continue.

  • 30 days free
  • Unlimited participants
  • No minimum term

Guide for owners

Frequently asked questions

Anything else on your mind? We are happy to help.

Talk to us

When the owner commits funds to the project. In Fidrel, whichever estimate you approve as the baseline is locked and becomes the original budget, and the later design-phase estimates are revisions compared with it.