One tenant improvement, worked by hand
Take six steps, all finish-to-start with no lag: demolition 3 days, framing 4, electrical rough-in 5, plumbing rough-in 3, drywall 6 after both rough-ins, paint 4, and a 2-day millwork install that waits for paint and for a 10-day cabinet fabrication that can start once demolition is done. The longest chain is demolition, framing, electrical, drywall, paint and install: 3 + 4 + 5 + 6 + 4 + 2 = 24 working days. Plumbing runs beside electrical and has 2 days of float. The cabinets start on day 4 and are not needed until day 23, so they have 9 days of float, and if the shop slips more than that, the cabinets become the critical path and the install date moves with them.