Link RFIs to the construction schedule and see what they block

An unanswered RFI can stall the work it is about, but the Gantt chart rarely shows it. The schedule and the RFI log live in different files, so the superintendent sees the late RFI and the scheduler sees a plan that still looks fine. Linking the two puts the block on the chart. Here is how to link them in Fidrel and what the link does and does not do.

30 days free · No long-term contract.

Fidrel’s schedule on a laptop, tablet and phone, with activities, milestones and today’s line in the Gantt chart

Why RFIs and the schedule drift apart

The block lives in someone’s head

Everyone on the team knows the curtain wall is waiting for an answer, yet the schedule shows a clean bar. New people join the lookahead meeting and the reason for the slip has to be explained again.

A late answer, a late argument

When the answer arrives after the activity should have started, the discussion about who is responsible starts from scratch, because nothing recorded which activity the question was holding.

Change orders without a trail

If the answer changes the scope, the change order is written separately. Weeks later it is hard to find which RFI, which activity and which change belong together.

What a blocking link does

A link marked Blocked flags the activity for as long as the RFI is not answered or closed. The activity gets an exclamation mark in the chart, hovering over it lists the RFI and its deadline, and the schedule’s key figures count the blocked activities. When the RFI is answered or closed the flag disappears on its own, with nothing to clear by hand. An RFI that is linked without the Blocked tick is a reference and flags nothing.

Scheduling
The Gantt chart in Fidrel with grouped activities, milestones and dependency lines, and a legend for baseline and actual progress

Other records an activity links to

The same Linked records panel links documents, issues, change orders and estimate line items to an activity. Only RFIs and issues can block it. A change order that follows from the RFI can be created from the RFI itself with New change order, and an NCR the same way with New NCR. The change order carries its own Schedule impact (days), which you enter.

Fidrel’s RFI register with RFI-0005 to RFI-0008 and their statuses, and one open RFI showing its question, recipient and deadline

How to link an RFI to an activity

  1. Step 1

    Open the activity’s links

    Open the activity and find Linked records. Choose Requests, which lists the project’s RFIs, search for the one you need and click it to add it to the activity.

  2. Step 2

    Mark it as blocking

    Tick Blocked, then click the RFI, if the activity cannot go ahead without the answer. The link shows Blocked in amber while the RFI is open, and the chart marks the activity with an exclamation mark.

  3. Step 3

    Follow it from both sides

    Open the RFI and the linked activity appears on it with its dates and a Blocked label; select it to jump to the schedule. When the RFI is answered or closed, the block clears by itself.

From the RFI to the change order

Say the answer adds scope. Create the change order from the RFI, and the title, location and responsible person carry over and the two are linked to each other. Then link the change order to the same activity, so the activity lists the RFI and the change order among its linked records and the chain from question to activity to change is on record.

Who can link

Linking is done by people who may edit the schedule. Everyone else with access sees the links and the Blocked flag.

What the link does not do

A blocking link flags the activity and records the connection; it does not move any dates. Fidrel does not calculate delay days or decide whether you are entitled to a time extension; Schedule impact (days) on a change order is a number you enter. Only RFIs and issues can block an activity; documents, change orders and estimate line items can be linked but never block it.

One project. One subscription. The entire platform included.

Your trial applies to your first own project and starts when that project is created. No card required. Afterwards, choose card or invoice to continue.

  • 30 days free
  • Unlimited participants
  • No minimum term

Schedule links

Frequently asked questions

Anything else on your mind? We are happy to help.

Talk to us

Yes. Link the same RFI to each activity and tick Blocked on each link, and every one of them is flagged until the RFI is answered or closed.