Which lines suit which pricing
Use a unit price where the work is measured and may change: concrete by volume, drywall by area, doors by each. A change in the drawings then flows through to the amount, and when a quantity was taken off a drawing the line is flagged if the drawing has changed since. Use a lump sum where nobody measures the work: mobilization, permits, an allowance, or a subcontractor’s quote that is one total. A quote that is a total is a lump sum by nature, and forcing it into a unit price would invent a quantity.