Master schedule vs subcontractor schedule

A general contractor often carries two schedules: the master schedule the owner sees, and a tighter one for the trades, with float held back for the contractor. The hard part is not building both, it is controlling who sees which. This page shows how a project in Fidrel holds several schedules, how the Internal and Shared switch works, and what a copy does and does not carry over.

30 days free · No long-term contract.

The Fidrel schedule on a laptop, tablet and phone, with activities, milestones and today’s line on the Gantt chart

Why two schedules are hard to run

The wrong schedule goes to the wrong person

When both versions live in files on a shared drive, one wrong attachment puts the contractor’s private float in front of the owner, or the owner’s milestone dates in front of a trade that now plans to them.

The copy drifts from the original

The trade schedule is usually a copy of the master with tighter dates. After a few weeks of updates nobody can say which activities were changed on purpose and which were simply never carried across.

Subs plan from a stale printout

A trade that works from last month’s PDF builds to dates that no longer exist. Everyone who needs the current schedule has to be able to open it, not wait for the next email.

Several schedules in one project

A project can have several schedules, and each one is either Shared or Internal. Shared is the default view for the team: administrators, participants and guests who have access to schedules. Internal is for project administrators only, and it can be shared later in one click. Making a schedule internal hides it from participants and guests everywhere, in search and the overview as well, and nothing in the schedule is deleted.

Scheduling
A schedule as a table in Fidrel, each activity with its start, end, duration, percent complete and responsible person

What a duplicate keeps and what it drops

The copy gets the same activities, dependencies and working calendar. Baselines, history and linked records are not copied, so the trade schedule starts without the master’s saved baseline and without the RFIs, issues and documents linked to its activities. That is deliberate for a working copy, but it means you should save a fresh baseline on the copy if you want to measure its variance.

The Gantt chart in Fidrel with activities as bars, their progress and the legend for baseline and actual progress

Running a master and a trade schedule in one project

  1. Step 1

    Build the master schedule

    Create the schedule for the project with Create schedule, add activities, milestones, dependencies and the working calendar, and keep it Shared if the owner and the team should see it.

  2. Step 2

    Duplicate it for the trades

    Choose Duplicate schedule. The copy is named with “(copy)” after the original and gets the same activities, dependencies and working calendar, so you can tighten dates without touching the master.

  3. Step 3

    Make the trade schedule Internal or Shared

    Click the Shared or Internal chip on a schedule. Internal means only project administrators see it; Shared means everyone in the project with access to schedules does. Fidrel asks you to confirm before it changes.

  4. Step 4

    Tag the activities by company

    Give each activity its Responsible, Company and Discipline, so the trade schedule can be filtered down to one subcontractor’s work. Export the chart as PNG, SVG or PDF for anyone outside the project.

Who can change which

Only project and organization administrators can change a schedule, whichever version it is. Participants and guests with access read it. Fidrel does not tie the two schedules together: nothing moves in the master when you move a date in the copy, so the contractor decides when and how the two are reconciled.

What Fidrel does not do between the two

Fidrel does not merge subcontractor schedules into the master or keep the two in step. Baselines, history and linked records are not copied when you duplicate a schedule. A subcontractor reads a schedule through a project account as a participant or guest, and a trade without an account can be given an exported chart. Fidrel is not a contract tool, so what the owner is entitled to see is for your agreement to say.

One project. One subscription. The entire platform included.

Your trial applies to your first own project and starts when that project is created. No card required. Afterwards, choose card or invoice to continue.

  • 30 days free
  • Unlimited participants
  • No minimum term

For general contractors

Frequently asked questions

Anything else on your mind? We are happy to help.

Talk to us

Yes. A project can have several schedules, and each one is either Shared with everyone who has schedule access or Internal to project administrators.