Fidrel

Site forms · ITR

Inspection and test record template (ITR), line by line

An inspection and test record is the proof that a piece of finished work was looked at before it was covered up or handed over: the right materials, built to the construction issue drawings and specification, within tolerance, sealed and connected, with its certificates in place. The template is simple. The discipline is filling it in at the work face rather than in the cabin, and keeping it unchanged afterwards. This page goes through Fidrel’s UK ITR template line by line and shows how it is filled in, adapted and locked.

30 days free · No minimum term.

Site forms in Fidrel on a laptop, a tablet and a phone, with completed forms listed and a form being filled in

Where ITRs lose their value

Ticked in the cabin at the end of the week

The ITR for a run of first-fix pipework is completed from memory on Friday, after the boarding has gone up. It records that an inspection should have happened, not that it did.

Certificates that never meet the record

The pressure test certificate is in the M&E subcontractor’s e-mail, the ITR says “attached”, and at handover nobody can put the two together for the flats it covers.

A record that can be tidied up later

An ITR kept as an editable spreadsheet can be corrected after a failure is discovered. A record that cannot change once it is submitted is the only kind worth showing a client.

ITR and ITP: the record and the plan

An inspection and test plan sets out, before work starts, what will be inspected and tested, by whom, against which criteria, and where the client or designer must witness or release the work. The inspection and test record is what is filled in when each of those inspections actually takes place, for a particular element or area. Fidrel’s ITR template describes itself as the contractor’s inspection of completed work against the inspection and test plan; the plan itself is a document you keep alongside it.

Site forms
The Templates tab of Site forms in Fidrel with the delivery inspection, permit to work, inspection & test record (ITR) and site safety inspection

The six lines of the UK template

Work complies with construction issue drawings and specification: the inspector checks against the current issue, not an earlier one. Materials and products as specified: what is installed matches what was approved, including any substitutions agreed through submittals. Dimensions, setting out and tolerances checked: positions, levels, falls and gaps are measured, not assumed. Connections and seals completed: joints, fixings, fire stopping and seals are finished before anything covers them. Certificates and test results attached: the evidence for any test exists and has been put with the project’s documents. Non-conformances and actions: a written line for anything that failed and what is to be done about it.

Completed site forms in Fidrel listed with their numbers, locations, inspectors, dates and status

Using the ITR in Fidrel

  1. Step 1

    Add the standard templates

    In Site forms open Templates and choose Add standard templates. In a UK project this adds the Inspection & test record (ITR) along with a site safety inspection, a delivery inspection and a permit to work template.

  2. Step 2

    Fit the ITR to the trade

    Edit the template, or make one per trade with New template: add check items, number items for readings such as a test pressure, or date items, and decide which items must be answered before the form can be submitted.

  3. Step 3

    Fill it in at the work

    Choose Fill in a form and the ITR, set Location / element to the part of the work inspected, such as Level 2, flats 201–206, and answer each item Pass, Fail or N/A on a phone, tablet or computer.

  4. Step 4

    Record actions and submit

    Write any non-conformances and actions in the text item, then Submit. Fidrel checks that every required item is answered, asks you to confirm, and locks the record so that it cannot be changed afterwards.

Making the template fit the work

The template belongs to the project once it is added, so it can be changed to suit each package. A drylining ITR might add board type, fixing centres and joint treatment; a plumbing ITR might add a number item for the test pressure and a date item for the test. Each item is a check answered Pass, Fail or N/A, a text, a number or a date, and any item can be made required. Forms already submitted keep their own copy of the items, so changing the template later does not alter them.

Locked on submission, counted in the list

A form can be saved as a draft while the inspection is in progress and submitted when it is complete. Once submitted it is locked for everyone, administrators included, and only drafts can be deleted. Completed forms are numbered F-001 onwards, newest first, with the location, the person who carried out the check and the date; each shows how many items were answered Fail, and the list can be searched by form, location or inspector and filtered by template.

ITR or inspection record?

Fidrel has two ways of recording an inspection. The ITR is a site form: a fixed checklist, answered line by line and locked. An inspection under Inspections & quality is a single record with a type, a responsible person, photos and a result of passed, remarks or failed, from which a non-conformance can be raised directly. Use the ITR where the client expects a completed checklist for each area, and an inspection record where the evidence is photographic or a failure must turn straight into an NCR.

What the ITR template does not do

Fidrel holds no inspection and test plan: there are no hold or witness points, no notice before one and nothing that stops work at one. Site forms hold no photos or attachments; certificates and test results are kept in the project’s documents, and the form records that they are there. A Fail on the ITR is counted but does not raise a non-conformance by itself. A submitted form cannot be printed or exported from Fidrel.

One project. One subscription. The entire platform included.

Your trial applies to your first own project and starts when that project is created. No card required. Afterwards, choose card or invoice to continue.

  • 30 days free
  • Unlimited participants
  • No minimum term

Site forms · ITR

Frequently asked questions

Anything else on your mind? We are happy to help.

Talk to us

A record, filled in at the time, that a specific piece of work was inspected or tested against the drawings and specification, with the result of each check and any actions.