How a commitment reaches the forecast
The estimate at completion is the invoiced amount plus what remains under the forecast or the commitments. Where nobody has entered a remaining forecast for a budget item, Fidrel uses the highest of the item’s current budget, its committed amount and its invoiced amount. A signed commitment above the budget therefore shows as a projected overrun at once, before any invoice exists. A financial alert, Commitments exceed budget, names the line, and the threshold alerts for consumption and for a rising forecast are set by a person with the budget permission.