O&M manual checklist: what each building system’s package holds

An O&M package is only useful if every system has its own manual and someone can see which ones have not arrived. This checklist sets out what the package for each building system commonly holds, then shows how the closeout checklist in Fidrel tracks each manual from missing to submitted to approved, system by system and trade by trade.

30 days free · No long-term contract.

Facility management in Fidrel on a laptop, tablet and phone

Where O&M packages fall short

One binder for the whole project, nothing per system

A single folder called O&M collects whatever the trades send. Months later the facility team opens it, finds the elevator manual but no controls diagram, and nobody can say who owed the missing pages.

Manuals arrive in pieces

The mechanical subcontractor sends equipment data in the spring and the controls contractor sends the sequences in the fall. Without a line per manual, a half-delivered package looks the same as a finished one.

Nobody owns the chase

Superintendents follow submittals and the punch list, and O&M manuals are left for the end. The owner’s staff find out what is missing when the first filter change comes due and no one knows the part number.

What an O&M package commonly holds, system by system

Your specifications decide what is required, so treat this list as a starting point for the closeout meeting. Elevators: maintenance manuals, controller wiring diagrams, emergency procedures and the service contact. Fire suppression: the riser and valve layout, pump and controller instructions, inspection and test instructions and a spare parts list. Plumbing: fixture and heater manuals, a valve schedule with tags, pump data and the data sheets for backflow devices. HVAC and building automation: equipment manuals, filter and belt schedules, control point lists and the sequences of operation. Electrical: panel schedules, switchgear and transformer manuals, lighting control and generator instructions. Communications and security: device lists, rack layouts and the manuals for access control and cameras. Envelope and roofing: care and maintenance instructions, sealant and coating data and the warranty documents. Finishes: product data, paint and flooring schedules, cleaning instructions and the attic stock list.

Operations
A closeout checklist in Fidrel with items approved, submitted and missing, and who approved an item and when

Eight system folders and a systems manual

The US folder structure holds a 03 O&M manuals folder with one subfolder each for elevators, fire suppression, plumbing, HVAC and building automation, electrical, communications and security, envelope and roofing, and finishes. A separate 04 Systems manual folder has subfolders for the systems manual as issued, the executive summary, the facility guide, the sequences of operation and the system schematics. The template adds checklist lines for HVAC and building automation, electrical, plumbing and the systems manual, which leaves the other four systems for you to add as New item lines.

The Export center in Fidrel, which downloads folders as one ZIP with a CSV list of the files

How to track O&M manuals by system in Fidrel

  1. Step 1

    Create the closeout checklist

    Open Closeout in facility management and choose Create from template. The US template adds O&M lines for HVAC and building automation, electrical and plumbing, plus the systems manual, and it skips any line already on the list.

  2. Step 2

    Add a line for every other system

    Select New item, type a title such as O&M manual – HVAC, pick the Operation and maintenance section, and name the Responsible party who must turn it over. Enter a due date so the line can be flagged once it passes.

  3. Step 3

    Point each line at its folder

    An administrator sets up the standard folder structure first. Link each line to the matching system folder under 03 O&M manuals; the trade then uses Upload to that folder, and the row shows how many documents it holds.

  4. Step 4

    Move each line through its status

    When a manual arrives, change the status to Submitted. Review it against your specification, then set Approved, which records who approved it and when. Use N/A for a system the building does not have.

A chase list by trade

Every row in the Operation and maintenance section shows the responsible party, a due date that is flagged once it is overdue, the status and, where a folder is linked, the folder and the number of documents in it. The section heading counts how many lines are approved or N/A out of the total, and a progress line for the whole checklist counts approved, submitted and missing. Scan the section for rows still marked Missing, read the name beside each, and you have the list to take to the next coordination meeting.

What the O&M checklist in Fidrel does not do

Fidrel holds and tracks the documents but does not write, compile or paginate the manual, and it produces no bookmarked PDF binder. The checklist is grouped by section and not by company, so there is no single list of everything one subcontractor still owes. Closeout items send no reminders, and approving an item is a status with a name and a date, not an e-signature. The checklist itself cannot be exported or printed. Contractors can upload to the folder an item points to when they may upload there, but only people who manage the checklist can mark an item Submitted or Approved.

One project. One subscription. The entire platform included.

Your trial applies to your first own project and starts when that project is created. No card required. Afterwards, choose card or invoice to continue.

  • 30 days free
  • Unlimited participants
  • No minimum term

Closeout documents

Frequently asked questions

Anything else on your mind? We are happy to help.

Talk to us

Commonly the equipment data, the manufacturer’s operating and maintenance instructions, parts lists, maintenance intervals, warranty information and the installer’s contact details. Your specifications set the requirement, and Fidrel only tracks the documents you ask for.